Receival of brick test report initiated in December
Receival of report for brick test sent to the lab on December. …
Removal of the gilt repousse plate
Removal of the gilt repousse plate from the ground floor garva griha completed. …
Archiving of metal repousse
Conservation and archiving work done for metal repousse, including the 108 lokeswara and various other elements. …
Work on art conservation lab set-up completed
Ongoing work on art conservation lab set-up completed. …
Scaffolding on north and west side
Scaffolding for worker's safety and efficiency completed on the north and west sides. …
Meeting with Community
A meeting was held to discuss on community's viewpoints on the project and to resolve any existing issues. …
Preparation of storage space
Material Heritage Storage for art objects work completed upto 80 % including wooden planks …
Structural Investigations
Pit B was carefully dug till 1.5m at the Garva Griha wall. Work at Pit B stopped due to sand filling up the pit continuously from the sides. INTACH, CLPIU to discuss interventions to be taken for strengthening of foundation based on INTACH …